- Wall Township Public Schools
- Progress Updates
Progress Updates As of October 8, 2024
-
Paving Upgrades at Allenwood Elementary School
- Awarded to Catel Inc
- Construction: July 2023 – October 27, 2023
- Construction Update:
- Punch List work in progress.
Paving Upgrades at West Belmar Elementary School
- Awarded to Catel Inc
- Construction: June 2024 – August 29, 2024
- Construction Update:
- Change Order issued for infill of septic tank
- Punch List work in progress
- Awaiting close out documents
Interior Alterations at Multiple Schools (Bid 1 – Toilets)
- Awarded to Catel Inc.
- Construction Phase 1: June 2024 – August 29, 2024
- Wall High School, West Belmar Elementary School, Wall Primary School
- Construction Phase 2: June 2025 – August 28, 2025
- Allenwood Elementary School, Central Elementary School, Old Mill Elementary School
- Construction Update:
- Punch List issued for Wall High School, West Belmar Elementary School and Wall Primary School.
- Punch List work in progress.
- Window Installation for Wall Primary School to occur over Winter Break or other school holiday.
HVAC Upgrades at Allenwood ES, Old Mill ES and West Belmar ES
- Project Awarded to Kappa Construction
- Construction: June 2025 – August 2025
- Phase 1: West Belmar Electrical Feeds: July 2024 – In coordination with Catel Inc.
- Phase 2: Boiler Work: June 1, 2025 to September 27, 2025
- Phase 3: Balance of Work: June 16, 2025 to August 29, 2025
- Construction Update:
- Phase 1 work is complete.
- Currently in submittal review phase.
- Due to refrigerant phase out units were shipped earlier than anticipated.
- RTUs to be stored at crane yard and at Kappa’s facility.
- Kappa is coordinating UV and FCU storage location.
- Double handling for UV and FCU will result in double handling charges and Kappa to submit a PCO for these costs.
Roofing Replacement at Multiple Schools
- Project awarded to Pravco Inc.
- Substantial Completion Date: August 30, 2024
- Construction update
- Work is substantially complete and Spiezle has issued punch lists for the work.
- Punch list work is in progress.
- $250,000 change order credit issued for remaining project allowance.
Interior Alterations at Multiple Schools (Bid 2 -WHS and WIS Educational Spaces, WIS Windows)
- Bid Advertised: August 29, 2024
- Bid Opening: September 26, 2024 at 11:00 am
- Low Responsible Bidder: The Bennett Company
- Total Bid: $14,150,000 (Includes all Alternates)
- Budget: $12,229,224
- Bid Award: October 15, 2024 TBD
- Phase 1: HS Auditorium and WIS Locker Room Construction: May 1, 2025 to August 29, 2025
- Phase 2: HS and WIS Art/Tech Classrooms, WIS Windows and Old Mill Nurse Suite: June 16, 2025 to August 29, 2025
HVAC Upgrades at Wall IS, Central ES and Wall High School
- Bid Advertisement: September 5, 2024
- Bid Opening: October 3, 2024 at 11:00 am
- Low Responsible Bidder: Preferred Mechanical
- Total Bid: $21,169,000 (Includes all Alternates)
- Budget: $14,062,025
- Bid Award: October 15, 2024 TBD
- Construction: June 2025 – August 2025
- Phase 1: Central School Boilers – June 2, 2025 to September 26, 2025
- Phase 2: Balance of Work – June 16, 2025 to August 29, 2025
Roofing Replacement at Wall HS and Old Mill ES
- Design: July to October 2025
- Bidding: November 2025
- Award: December 2025
- Construction: June 2026 – August 2026
Athletic Field Upgrades at Wall High School
- Bidding: February 2025
- Award: February/March 2025
- Construction: Summer 2025 to Fall 2025
- Status Update:
- Spiezle and District to meet on October 11, 2024 to kick off project design.