Progress Updates As of October 8, 2024

  • Paving Upgrades at Allenwood Elementary School

    • Awarded to Catel Inc
    • Construction: July 2023 – October 27, 2023
    • Construction Update:
      • Punch List work in progress.

    Paving Upgrades at West Belmar Elementary School

    • Awarded to Catel Inc
    • Construction: June 2024 – August 29, 2024
    • Construction Update:
      • Change Order issued for infill of septic tank
      • Punch List work in progress
      • Awaiting close out documents

    Interior Alterations at Multiple Schools (Bid 1 – Toilets)

    • Awarded to Catel Inc.
    • Construction Phase 1: June 2024 – August 29, 2024
      • Wall High School, West Belmar Elementary School, Wall Primary School
    • Construction Phase 2: June 2025 – August 28, 2025
      • Allenwood Elementary School, Central Elementary School, Old Mill Elementary School
    • Construction Update:
      • Punch List issued for Wall High School, West Belmar Elementary School and Wall Primary School.
      • Punch List work in progress.
      • Window Installation for Wall Primary School to occur over Winter Break or other school holiday.

    HVAC Upgrades at Allenwood ES, Old Mill ES and West Belmar ES

    • Project Awarded to Kappa Construction
    • Construction: June 2025 – August 2025
      • Phase 1: West Belmar Electrical Feeds: July 2024 – In coordination with Catel Inc.
      • Phase 2: Boiler Work: June 1, 2025 to September 27, 2025
      • Phase 3: Balance of Work: June 16, 2025 to August 29, 2025
    • Construction Update:
      • Phase 1 work is complete.
      • Currently in submittal review phase.
      • Due to refrigerant phase out units were shipped earlier than anticipated.
        • RTUs to be stored at crane yard and at Kappa’s facility.
        • Kappa is coordinating UV and FCU storage location.
        • Double handling for UV and FCU will result in double handling charges and Kappa to submit a PCO for these costs.

    Roofing Replacement at Multiple Schools

    • Project awarded to Pravco Inc.
    • Substantial Completion Date: August 30, 2024
    • Construction update
      • Work is substantially complete and Spiezle has issued punch lists for the work.
      • Punch list work is in progress.
      • $250,000 change order credit issued for remaining project allowance.

    Interior Alterations at Multiple Schools (Bid 2 -WHS and WIS Educational Spaces, WIS Windows)

    • Bid Advertised: August 29, 2024
    • Bid Opening: September 26, 2024 at 11:00 am
      • Low Responsible Bidder: The Bennett Company
      • Total Bid: $14,150,000 (Includes all Alternates)
      • Budget: $12,229,224
    • Bid Award: October 15, 2024 TBD
    • Phase 1: HS Auditorium and WIS Locker Room Construction: May 1, 2025 to August 29, 2025
    • Phase 2: HS and WIS Art/Tech Classrooms, WIS Windows and Old Mill Nurse Suite: June 16, 2025 to August 29, 2025

    HVAC Upgrades at Wall IS, Central ES and Wall High School

    • Bid Advertisement: September 5, 2024
    • Bid Opening: October 3, 2024 at 11:00 am
      • Low Responsible Bidder: Preferred Mechanical
      • Total Bid: $21,169,000 (Includes all Alternates)
      • Budget: $14,062,025
    • Bid Award: October 15, 2024 TBD
    • Construction: June 2025 – August 2025
      • Phase 1: Central School Boilers – June 2, 2025 to September 26, 2025
      • Phase 2: Balance of Work – June 16, 2025 to August 29, 2025

    Roofing Replacement at Wall HS and Old Mill ES

    • Design: July to October 2025
    • Bidding: November 2025
    • Award: December 2025
    • Construction: June 2026 – August 2026

    Athletic Field Upgrades at Wall High School

    • Bidding: February 2025
    • Award: February/March 2025
    • Construction: Summer 2025 to Fall 2025
    • Status Update:
      • Spiezle and District to meet on October 11, 2024 to kick off project design.